Atlantic Link Energy Solicitation Issued January 11, 2017
Notice of Intention to Submit a Proposal due January 20, 2017
Participant conference (Meeting in Halifax, NS + WebEx) January 25, 2017, 12:30 p.m. AST 
Mutual Confidentiality Agreement Due February 8, 2017
Individual meetings with proponents Week of February 20, 2017
Draft Letters of Credit Submitted for Review by Emera March 24, 2017
Deadline for submitting written questions March 31, 2017
Responses to questions posted to web site April 11, 2017
Deadline for Electronic Proposals, by 3:00 pm (EST) April 19, 2017
Deadline for Proposal Security Submission, 3:00 pm (EST) April 19, 2017
Deadline for Hard Copy Submission, by 5:00 pm (EST) April 21, 2017
Deadline for Supplemental MA Materials, by 5:00 pm (EST) April 26, 2017
Proposal Evaluation Period (estimated) May 17, 2017
Notification to Proponents (estimated) May 17, 2017
 Deadline for Hydroelectric Submission Materials and Proposal Security, by 1:00 PM (EST)  May 23, 2017
PPAs executed June 9, 2017
Projects in-service by (See Guidance #1 - COD Coordination) Q4, 2022